? ? ? ?The Heidelberg Congo Gold CILU project, which was contracted by the Tianjin Institute, was officially put into production at 19:58 pm local time on February 26, 2019.
The contract for this project officially came into effect on November 29, 2017. The contract period lasted for 19 months. With the joint efforts of the project personnel, the political situation of local election turmoil and the epidemic of complex infectious diseases such as Ebola and malaria were overcome. It took 14 months and 26 days to complete the project construction safely and put into production smoothly as scheduled.