Jingshi Cement Co., Ltd.'s cement production line with an annual output of 1.5 million tons is funded and constructed by Yafei Group Co., Ltd. and is contracted by Tianjin Cement Industry Design and Research Institute Co., Ltd. Our company is responsible for the construction of Bid Section B. The construction contents mainly include: equipment installation, steel structure installation, electrical installation, pipeline installation, insulation and other projects in the Bid Section B area. The project is 280KM away from Windhoek, the capital of Namibia, and about 8 kilometers away from the city of Ochwarongo. Part of the first phase cement grinding station of the entire project has been put into operation, and part of the second phase clinker line is now under construction. So far, the pulverized coal silo and raw coal silo have been completed, and other steel structures are in the process of production and installation.
?
?
?