At the end of 2022, our company will undertake the completion, elimination and improvement of civil and electromechanical engineering of this project. The main content includes the unfinished construction content of each discipline of the project (equipment installation, electrical, steel structure, civil engineering and yard roads, etc.). Our company dispatched professional personnel to carefully sort out the project and actively organized professional technical forces to carry out the construction of the unfinished items., rectification, renovation, maintenance and coordination with debugging.
In mid-February 2023, our company cooperated with the general contractor's debugging team to successfully put the cement mill into production; in August 2023, the construction of unfinished items such as civil engineering, electrical, equipment, and steel structures was completed. As of November 2023, after more than 8 months of hard work, the project is about to complete the TOC and be handed over to the completion stage.
?
?
?
?
Contribution by Wu Jianhui